Which of the following statements is most accurate about the critical path?

A.
The critical path is always one path that shows the project duration.
Answers
A.
The critical path is always one path that shows the project duration.
B.
The critical path has no float.
Answers
B.
The critical path has no float.
C.
The critical path is the longest path because it has the most activities.
Answers
C.
The critical path is the longest path because it has the most activities.
D.
The critical path reveals which path has the most risk of failure.
Answers
D.
The critical path reveals which path has the most risk of failure.
Suggested answer: B