You are the program manager for the BHN Program. Your program has 122 stakeholders that you'll need to plan to communicate with. Considering the size of the program how many communication channels do you have in this program?

A.
244
Answers
A.
244
B.
122
Answers
B.
122
C.
14,884
Answers
C.
14,884
D.
7,381
Answers
D.
7,381
Suggested answer: D