Question 61 - PgMP discussion
You are the program manager for your organization. You have created a program that will create things for the organization throughout the program not only at program closure. All of the following are elements that you may transfer to the organization throughout the program's life cycle except for which one?
A.
Benefits
B.
Risk management outcomes
C.
Program personnel
D.
Outputs from team development