You are the program manager for your organization and are planning the program. One of the plans you need to create will define how you'll transfer the benefits of the program to the operations of your organization. Which program management plan defines this process?

A.
Operational transfer plan
Answers
A.
Operational transfer plan
B.
Program transition plan
Answers
B.
Program transition plan
C.
Benefits transfer plan
Answers
C.
Benefits transfer plan
D.
Program closure plan
Answers
D.
Program closure plan
Suggested answer: B