You are the program manager for your organization. Your current program is to create a new recreational facility in your city. Franklin, the Chief Executive Officer, is concerned about meeting all of the financial and schedule requirements of the proposed program. Martina, the mayor of your town, wants to make certain the program meets all safety requirements and building codes. Your supervisor, Mary Ann, is the Program Director, and she is concerned about the start date of your program. Another stakeholder, Hal, is worried that your resources may be spread thin on the program as some of the resources are on multiple projects in your program. To whom will you report to in this program?

A.
Franklin
Answers
A.
Franklin
B.
Martina
Answers
B.
Martina
C.
Hal
Answers
C.
Hal
D.
Mary Ann
Answers
D.
Mary Ann
Suggested answer: D
asked 23/09/2024
Wilker Aguiar
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first