What should a program manager do when a scope change has been approved that will drastically affect the program costs assuming that the costs will be added to the program budget?
A.
Adjust the cost baseline
B.
Communicate cost of the change to all stakeholders
C.
Adjust the quality baseline
D.
Communicate the change to all stakeholders