List of questions
Related questions
Question 94 - PgMP discussion
You are the program manager of the JNH Program. Tom, a project manager in your program, has just completed his project and is ready to officially close his project. You agree that Tom's project is completed. What role do you play in Tom's project closure?
A.
You must ensure that the project sponsor closes the project.
B.
You must ensure that that the projects within the program have been closed at the project level.
C.
You must close the project before operations closes the project.
D.
You must ensure that the program management team closes the project for the project manager.
Your answer:
0 comments
Sorted by
Leave a comment first