Which one of the following is NOT a component of the risk monitoring and controlling process?

A.
Executing risk response plans
Answers
A.
Executing risk response plans
B.
Completing quantitative risk analysis
Answers
B.
Completing quantitative risk analysis
C.
Tracking identified risks
Answers
C.
Tracking identified risks
D.
Determining if new risks have developed
Answers
D.
Determining if new risks have developed
Suggested answer: B