Question 96 - PgMP discussion

Report
Export

You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

A.
Program administrative closure
Answers
A.
Program administrative closure
B.
Enterprise environmental factors
Answers
B.
Enterprise environmental factors
C.
Closing processes
Answers
C.
Closing processes
D.
Organizational process assets
Answers
D.
Organizational process assets
Suggested answer: B