Question 149 - PgMP discussion

Report
Export

You are the program manager for your organization and your team has reported on a new issue among your program stakeholders. You want to address this issue as soon as possible, but it will need to be studied and reviewed. You recommend that Shirley, one of your program team members, study the issue and present a few solutions in a week's time. What else should you do with the issue?

A.
Determine the time and cost of researching the issue for resolution.
Answers
A.
Determine the time and cost of researching the issue for resolution.
B.
Record the issue in the issue log.
Answers
B.
Record the issue in the issue log.
C.
Document the issue in the lessons learned.
Answers
C.
Document the issue in the lessons learned.
D.
Communicate with the stakeholders that you are addressing the issue.
Answers
D.
Communicate with the stakeholders that you are addressing the issue.
Suggested answer: B