Performing quality assurance in a program can result in which one of the following?

A.
Quality control execution
Answers
A.
Quality control execution
B.
Scope fulfillment
Answers
B.
Scope fulfillment
C.
Quality management plan
Answers
C.
Quality management plan
D.
Change requests
Answers
D.
Change requests
Suggested answer: D