Question 151 - PgMP discussion
You are the program manager for your organization. This program will last for two years and has eight projects. The cost of your program is $4 million and there are some risk concerns that may affect the overall cost of the program. Management is concerned with how long it will take the program to reach the management horizon. What is management horizon also known as?
A.
Payback period
B.
Cost performance index
C.
Cost-to-benefits ratio
D.
Return on investment