You are the program manager for your organization. One of the projects within your program is to install 15,000 light fixtures throughout your organization's corporate campus. The new fixtures will save on electrical costs. Which one of the following choices is an ideal approach to quality assurance and the installation of the light fixtures for this project team?

A.
The cost and time of each installation should go down because of the learning curve.
Answers
A.
The cost and time of each installation should go down because of the learning curve.
B.
The project manager should work with the project team to understand how each fixture is to be installed.
Answers
B.
The project manager should work with the project team to understand how each fixture is to be installed.
C.
The project team members should develop their own system for installation of the fixtures.
Answers
C.
The project team members should develop their own system for installation of the fixtures.
D.
Use a checklist for the installation because it is repeatable work.
Answers
D.
Use a checklist for the installation because it is repeatable work.
Suggested answer: D