Gary is program manager for his organization. His current program is over budget and is slipping on the program schedule. Management has demanded a change to the program scope. What is the most likely type of change management would make to this program scope?

A.
A change to add additional funds to the program scope
Answers
A.
A change to add additional funds to the program scope
B.
A change to reduce the program scope
Answers
B.
A change to reduce the program scope
C.
Anything that management demands
Answers
C.
Anything that management demands
D.
A change to add additional time to the program schedule
Answers
D.
A change to add additional time to the program schedule
Suggested answer: B