Question 318 - PgMP discussion

Report
Export

While setting up a program's infrastructure and plan, a program management team develops documents and processes that provide commonality and consistency throughout the program's components. What should the team also prepare, if not already provided by the organization's assets?

A.
Breakdowns such as the program work breakdown structure (PWBS), component project milestones, and budgets that transform top-level planning into fragments relevant to the components
Answers
A.
Breakdowns such as the program work breakdown structure (PWBS), component project milestones, and budgets that transform top-level planning into fragments relevant to the components
B.
Industry standards that provide guidance to the component project managers on how to adapt their detailed planning to the program's master plan
Answers
B.
Industry standards that provide guidance to the component project managers on how to adapt their detailed planning to the program's master plan
C.
Documents that enable level-adequate aggregation and consolidation of component/program information and forecasting
Answers
C.
Documents that enable level-adequate aggregation and consolidation of component/program information and forecasting
D.
Files, filing structures, and templates for knowledge repositories that contain centrally stored and commonly maintained program data
Answers
D.
Files, filing structures, and templates for knowledge repositories that contain centrally stored and commonly maintained program data
Suggested answer: A