The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's life cycle.

Which of the following would the customer be interested in reviewing?

A.
Estimate to complete
Answers
A.
Estimate to complete
B.
Estimate at completion
Answers
B.
Estimate at completion
C.
Original cost baseline
Answers
C.
Original cost baseline
D.
Cost performance index
Answers
D.
Cost performance index
Suggested answer: D