Question 328 - PgMP discussion
A program manager for an electronic gaming manufacturer is managing a new virtual reality program. An international trade agreement in the final stages of renegotiation will reduce supply-chain costs and delivery intervals. A materials supplier informs the program manager that when this agreement is finalized, it will shorten the product's delivery time.
What should the program manager update first?
A.
Procurement management plan
B.
Benefits register
C.
Risk register
D.
Benefits management plan
Your answer: