Question 330 - PgMP discussion
A program with six projects has been running for three years. The company's procurement and contracts department has compiled a qualified seller list. The program manager determines that one of the projects must be outsourced.
The program manager will use the qualified seller list to do which of the following?
A.
Plan a proposal evaluation system
B.
Prepare the program procurement management plan
C.
Perform the required program budget updates
D.
Issue requests for proposals