A program manager at a pharmaceutical company plans a new drug development effort. The development is slated to yield three drug variants. The program manager articulates the program scope boundaries.

Which of the following deliverables captures these items?

A.
Program scope management plan
Answers
A.
Program scope management plan
B.
Program governance plan
Answers
B.
Program governance plan
C.
Program scope statement
Answers
C.
Program scope statement
D.
Program work breakdown structure
Answers
D.
Program work breakdown structure
Suggested answer: C