Question 332 - PgMP discussion
A component project of a program is completed, and will provide the intended incremental benefits. How should the program manager proceed with the component transition?
A.
Update the program stakeholder engagement plan with stakeholders from the transition organization
B.
Define the component project's business value in the benefits management plan
C.
Update the program roadmap to reflect completion of a key end-point objective
D.
Initiate a program change request to close out the component project