Question 333 - PgMP discussion
A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components' strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools.
Which of the following must be addressed?
A.
Program performance monitoring and controlling
B.
Program management information system (PMIS)
C.
Program delivery management
D.
Program roadmap