Which of the following serves as a guiding principle for a program manager when preparing a program work breakdown structure?

A.
Decompose the program work based upon available resources
Answers
A.
Decompose the program work based upon available resources
B.
Decompose the program to the work package level
Answers
B.
Decompose the program to the work package level
C.
Decompose the program to the architecture baseline level
Answers
C.
Decompose the program to the architecture baseline level
D.
Decompose the program at a level sufficient to achieve control
Answers
D.
Decompose the program at a level sufficient to achieve control
Suggested answer: A