A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST).

What should the program manager update?

A.
Program communications management plan
Answers
A.
Program communications management plan
B.
Benefits management plan
Answers
B.
Benefits management plan
C.
Stakeholder engagement plan
Answers
C.
Stakeholder engagement plan
D.
Benefits transition plan
Answers
D.
Benefits transition plan
Suggested answer: B