Question 338 - PgMP discussion
A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST).
What should the program manager update?
A.
Program communications management plan
B.
Benefits management plan
C.
Stakeholder engagement plan
D.
Benefits transition plan