A program receives initial approval from the selection committee to proceed with the program development. What should the program manager do next?
A.
Define the program architecture and assign the benefits realization to the component projects.
B.
Complete the program setup to establish a firm foundation of support and approval for the program.
C.
Analyze lessons learned and historical information to validate the program's expected outcomes.
D.
Continue to develop the high-level program road map.