ExamGecko
Home Home / PMI / PgMP
Question list
Search
Search

List of questions

Search

Related questions











Question 340 - PgMP discussion

Report
Export

The program manager of a multinational program must reconcile data including subject matter experts' labor hour estimates, and other direct resource hour estimates. In addition, the program manager must prepare the cash flow analysis.

Which of the following should be considered to get a baseline budget?

A.
Currency exchange rates
Answers
A.
Currency exchange rates
B.
Component cost estimates
Answers
B.
Component cost estimates
C.
Baseline schedule
Answers
C.
Baseline schedule
D.
Program payment schedules
Answers
D.
Program payment schedules
Suggested answer: B
asked 23/09/2024
Nivi Kolatte
39 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first