The program manager of a multinational program must reconcile data including subject matter experts' labor hour estimates, and other direct resource hour estimates. In addition, the program manager must prepare the cash flow analysis.
Which of the following should be considered to get a baseline budget?
A.
Currency exchange rates
B.
Component cost estimates
C.
Baseline schedule
D.
Program payment schedules