Program manager B leaves the program and program manager A takes over the program responsibilities. Program manager A wants to ensure that all expected benefits of the program are realized.

What is used to assess the program cost/benefit justification?

A.
Program charter
Answers
A.
Program charter
B.
Benefits management plan
Answers
B.
Benefits management plan
C.
Program business case
Answers
C.
Program business case
D.
Program scope statement
Answers
D.
Program scope statement
Suggested answer: D