A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.

What should the program manager do to address these key stakeholders' concerns?

A.
Meet with the stakeholders and update the stakeholder map.
Answers
A.
Meet with the stakeholders and update the stakeholder map.
B.
Create a progress report to share with stakeholders after the next status meeting.
Answers
B.
Create a progress report to share with stakeholders after the next status meeting.
C.
Capture stakeholder expectations, and revise the stakeholder engagement plan.
Answers
C.
Capture stakeholder expectations, and revise the stakeholder engagement plan.
D.
Update the communications management plan after meeting with the program steering committee.
Answers
D.
Update the communications management plan after meeting with the program steering committee.
Suggested answer: C