A program completes all component projects and all identified benefits are being delivered. However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters.

To ensure the realization of long-term benefits, what should the program manager use?

A.
Benefits register
Answers
A.
Benefits register
B.
Benefits sustainment plan
Answers
B.
Benefits sustainment plan
C.
Benefits management plan
Answers
C.
Benefits management plan
D.
Benefits transition plan
Answers
D.
Benefits transition plan
Suggested answer: A

Explanation:

Reference: https://uwaterloo.ca/ist-project-management-office/methodologies/program-management/program-benefit-delivery/benefits-register