Question 374 - PgMP discussion
During program execution, a program manager receives feedback from an executive sponsor that some program stakeholders may not understand the intended benefits of the program.
Which will provide the greatest value to clarify stakeholder perceptions?
A.
Performing a stakeholder analysis
B.
Updating the stakeholder communications requirements
C.
Redistributing the benefits management plan
D.
Redistributing the program charter
Your answer: