The program sponsor returns from a board of directors meeting after identifying a significant risk to the program schedule. This may impact the program's benefits realization.
What should the program manager do next?
A.
Update the program benefits management plan and risk register.
B.
Implement the mitigation plan for the identified risk.
C.
Adjust the program scope to avoid the risk.
D.
Document the risk and create a mitigation plan.