ExamGecko
Home Home / PMI / PgMP
Question list
Search
Search

List of questions

Search

Related questions











Question 423 - PgMP discussion

Report
Export

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting.

What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program?

A.
Note stakeholder communication needs in the program charter and document their expectations in the benefits sustainment plan.
Answers
A.
Note stakeholder communication needs in the program charter and document their expectations in the benefits sustainment plan.
B.
Note stakeholder communication needs in the communications management plan and document their expectations in the benefits management plan.
Answers
B.
Note stakeholder communication needs in the communications management plan and document their expectations in the benefits management plan.
C.
Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits management plan.
Answers
C.
Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits management plan.
D.
Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits sustainment plan.
Answers
D.
Meet with the stakeholder to ensure stakeholder communication needs are documented in the communications management plan and that their expectations of benefits are documented in the benefits sustainment plan.
Suggested answer: C
asked 23/09/2024
Kristi Riddick
29 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first