A company is rolling out an innovative program that includes new processes intended to define how the company will manage future programs. While program execution is going well, the program sponsor is concerned that the knowledge acquired needs to be reused for future programs.

What should the program manager do to ensure that the knowledge acquired is captured efficiently?

A.
Record lessons learned in the program management plan
Answers
A.
Record lessons learned in the program management plan
B.
Create training materials summarizing team experiences and lessons learned
Answers
B.
Create training materials summarizing team experiences and lessons learned
C.
Direct the project managers to create event logs to document their experiences and lessons learned
Answers
C.
Direct the project managers to create event logs to document their experiences and lessons learned
D.
Organize review sessions after each program stage to document successes, issues, and lessons learned
Answers
D.
Organize review sessions after each program stage to document successes, issues, and lessons learned
Suggested answer: A