Question 438 - PgMP discussion
A software deployment program for a multinational organization requires the engagement of subcontractors. During the program planning phase, the contracts manager informs the program manager that the primary subcontractor's agreement includes incentives that would potentially conflict with program objectives.
What should the program manager do first?
A.
Review the contracts, and create a program budget contingency.
B.
Draft a change request for approval by the program steering committee.
C.
Ask the program management office (PMO) to conduct a risk assessment.
D.
Review the program charter, and update program objectives accordingly.