List of questions
Related questions
Question 439 - PgMP discussion
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.
How should the program manager demonstrate the program's progress?
A.
Define the key performance indicators (KPIs) for the program's outcome.
B.
Invite the key stakeholder to review the program charter and the program objectives.
C.
Provide additional program performance reports to the key stakeholder.
D.
Maintain the benefits register and provide it to the key stakeholder.
Your answer:
0 comments
Sorted by
Leave a comment first