During the last requirements meeting, Cloud Kicks team members said they will be attending a conference next week.

What should a consultant do in response to this news?

A.
Use the downtime to develop User Acceptance Testing (UAT) scripts.
Answers
A.
Use the downtime to develop User Acceptance Testing (UAT) scripts.
B.
Ask the client to sign off on requirements and start the Build phase.
Answers
B.
Ask the client to sign off on requirements and start the Build phase.
C.
Update the project plan and communicate it to stakeholders.
Answers
C.
Update the project plan and communicate it to stakeholders.
Suggested answer: C

Explanation:

When project teams inform about events such as attending a conference, it impacts the project timeline. The best practice in such scenarios is to update the project plan to reflect any changes due to the team's unavailability. This ensures that all stakeholders are aware of the adjustments, and the project can proceed smoothly without unexpected delays. According to Salesforce's project management best practices, keeping an updated project plan and clear communication with stakeholders is crucial for maintaining project alignment and ensuring transparency throughout the project lifecycle.