The project at Universal Containers is almost finished and now it is time to test the changes and updates that have been made before go-live.

Partial and Full sandboxes are unavailable.

Where should the consultant recommend testing be conducted?

A.
Create a new Developer Edition org and populate it with data.
Answers
A.
Create a new Developer Edition org and populate it with data.
B.
Create test accounts and opportunities in a new Trailhead Playground org.
Answers
B.
Create test accounts and opportunities in a new Trailhead Playground org.
C.
Create a new Developer sandbox and populate it with data.
Answers
C.
Create a new Developer sandbox and populate it with data.
Suggested answer: C

Explanation:

When Partial and Full sandboxes are unavailable, the consultant should recommend creating a new Developer sandbox and populating it with data for testing. A Developer sandbox provides a copy of the configuration (metadata) from the production environment and can be used to perform testing. While it has a limited data storage capacity, test data can be created or imported to simulate real-world scenarios. This approach ensures that the changes and updates are thoroughly tested before go-live.