Question 1 - PSM II discussion
The relationship between the Product Owner and the Developers has degraded over time.
The Developers are growing increasingly angry with the Product Owner for changing the requirements all the time and not being available enough. The Product Owner is angry with the Developers for changing requirements during implementation. What guidance should the Scrum Master offer?
(choose the best answer)
A.
Take everyone to a 2-day off-site event to relax and re-align. It is liberating to take people's minds away from work.
B.
Ask each person's functional manager to instruct their employees that they must collaborate better, or be removed from the team.
C.
Address why requirements change during the Sprint Retrospective. Ask the Developers and the Product Owner to talk about why the requirements are changing and consider the impact on value during this discussion.
D.
Ask for a project manager or other external resource to mediate and temporarily take over for the Product Owner.
Your answer:
0 comments
Sorted by
Leave a comment first