Question 50 - PSM II discussion
One Scrum Team is developing a product. They track how much software they produce as velocity. Their current velocity is 18 units of done work. A second team will be added to work on the same product. What is the most likely impact on the velocity of the original team?
(choose the best answer)
A.
Their velocity is likely to increase and be higher than 18.
B.
Their velocity is likely to decrease and be lower than 18.
C.
Their velocity is likely to be not affected and stay at 18.
Your answer: