Question 16 - PSM II discussion
During the Sprint Retrospective, the newest developer says that his perspective and ideas have been ignored by the rest of the Developers throughout the Sprint What Scrum values are touched here?
(choose the best three answers)
A.
Focus
B.
Courage
C.
Transparency
D.
Openness
E.
Respect
F.
Commitment