A few members of the Scrum Team discuss work that is not being done. Some say it is part of the Definition of Done, others say it is not. After an hour of angry discussion, someone starts making personal insults and anger levels rise. What is the best action for the Scrum Master to take?

(choose the best answer)

A.
Defuse the conflict. Take the Definition of Done and tell the other members of the Scrum Team how to interpret it, so they can autonomously decide whether the debated work is or is not part of it
Answers
A.
Defuse the conflict. Take the Definition of Done and tell the other members of the Scrum Team how to interpret it, so they can autonomously decide whether the debated work is or is not part of it
B.
Conduct a session to help the Scrum Team resolve the conflict and create a uniform Definition of Done. Remind the other members of the Scrum Team that conflicting ideas are natural, but making it personal does not help.
Answers
B.
Conduct a session to help the Scrum Team resolve the conflict and create a uniform Definition of Done. Remind the other members of the Scrum Team that conflicting ideas are natural, but making it personal does not help.
C.
End the discussion. Make the call whether the work is or is not part of the Definition of Done. Identify who is involved in the conflict and decide on their further presence on the Scrum Team.
Answers
C.
End the discussion. Make the call whether the work is or is not part of the Definition of Done. Identify who is involved in the conflict and decide on their further presence on the Scrum Team.
D.
Take the people involved aside. Ask them to resolve the situation outside of the Scrum Team, if required through their managers. The goal is to maintain stability in the team.
Answers
D.
Take the people involved aside. Ask them to resolve the situation outside of the Scrum Team, if required through their managers. The goal is to maintain stability in the team.
Suggested answer: B

Explanation:

The best action for the Scrum Master to take in this situation is to conduct a session to help the Scrum Team resolve the conflict and create a uniform Definition of Done.This is because the Scrum Master is a servant-leader, a facilitator, and a coach to the team, who should have the skills to help resolve conflicts if called upon by the team1.The Scrum Master can employ various strategies to effectively resolve conflicts within the Scrum Team, such as promoting open communication, facilitating active listening, mediating disagreements, and fostering collaboration2.The Scrum Master can also remind the team members that conflicting ideas are natural and can be beneficial for innovation and learning, but making it personal does not help and violates the Scrum values of respect and openness3.The Scrum Master can guide the team to create a clear and shared Definition of Done that reflects their quality standards and expectations for the product4.

The other options are not the best actions for the Scrum Master to take, because they either undermine the self-organization and autonomy of the team, escalate the conflict, or avoid addressing the root cause of the problem.