Question 20 - PSM II discussion
The Developers are waiting for an external supplier to deliver a specific product component that they need to integrate and use. Without that component there will not be enough work in the next Sprint to occupy the full team. They ask their Product Owner to re-order the Product Backlog. The Product Owner asks the Scrum Master for help. What would be good advice for the Product Owner?
(choose the best answer)
A.
Tell the Product Owner that the Product Backlog needs to be re-ordered to maximize utilization of the Developers. It is important to keep productivity high through proper use of the capacity available
B.
Tell the Product Owner that his primary concern is the flow of value reflected in the ordering of the Product Backlog. Timeline of the flow might be influenced by such dependencies and require some level of Product Backlog re-ordering
C.
Tell the Product Owner to remove all work involving the external component from the Product Backlog and create a new backlog for it. The work can then be planned in one or more separate Sprints as soon as the component is available.