Question 52 - PSM II discussion
You are a Scrum Master and one of the Developers approaches you and says: Every Sprint we are not completing regression testing for all of the selected Product Backlog items in the Sprint, but regression testing is part of the Definition of Done. We have discussed with the Product Owner and during the Sprint we decided to change the Definition of Done to remove regression testing. Which two actions are appropriate in this situation?
(choose the best two answers)
A.
Agree with altering the Definition of Done, if both the Developers and Product Owner agree.
B.
Ask the Developers and the Product Owner if removing regression testing from the Definition of Done allows the team to produce useful and valuable Increments at the end of every Sprint?
C.
Ask the Developers and the Product Owner what problem they are going to solve by altering the Definition of Done during the Sprint to remove regression testing. Will this raise transparency or improve quality?
D.
Disagree with the decision and tell them that having a stringent Definition of Done is important for the quality of the product, and they need to follow it.