Question 73 - PSM II discussion
What action should a Scrum Master take if the Development Team has decided that Retrospectives are no longer necessary?
A.
Start facilitating more productive and useful Retrospectives.
B.
Suggest reducing the frequency of the Retrospectives.
C.
Extend the Sprint time-box in order to fit the Retrospectives.
D.
Comply with the team's decision.
Your answer:
0 comments