Question 34 - PSPO-I discussion
During a Sprint, when is new work or further decomposition of work added to the Sprint
Backlog?
(choose the best answer)
A.
During the Daily Scrum after the Developers approve it.
B.
When the Scrum Master has time to enter it.
C.
When the Product Owner identifies new work.
D.
As soon as possible after it is identified.