Question 40 - PSPO-I discussion

Report
Export

As the Developers start work during the Sprint, they realize they have selected too much work to finish in the Sprint. What should they do?

(choose the best answer)

A.
Find another Scrum Team to give the excess work to.
Answers
A.
Find another Scrum Team to give the excess work to.
B.
As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.
Answers
B.
As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.
C.
Inform the Product Owner at the Sprint Review, but prior to the demonstration.
Answers
C.
Inform the Product Owner at the Sprint Review, but prior to the demonstration.
D.
Reduce the Definition of Done and get all of the Product Backlog items done by the new definition.
Answers
D.
Reduce the Definition of Done and get all of the Product Backlog items done by the new definition.
Suggested answer: B

Explanation:

This is the best answer because it respects the Scrum values of openness, commitment, and focus. The Developers should be transparent about their progress and collaborate with the Product Owner to adjust the Sprint scope accordingly. The Product Owner is responsible for maximizing the value of the product and the work of the Developers, so he or she should be involved in any decisions that affect the Sprint Goal and the Product Backlog.Reference:

Scrum Guide, page 10: "If the work turns out to be different than the Developers expected, they collaborate with the Product Owner to negotiate the scope of Sprint Backlog within the Sprint."

Scrum Guide, page 11: "The Product Owner is accountable for maximizing the value of the product resulting from the work of the Scrum Team."