Question 47 - PSPO-I discussion
What might indicate to a Product Owner that she needs to work more with the Scrum Team?
(choose the best answer)
A.
The acceptance criteria do not appear to be complete.
B.
She is not working full time with the Scrum team.
C.
People leave the Scrum Team.
D.
The Increment presented at the Sprint Review does not reflect what she thought she had asked for.