Question 57 - PSPO-I discussion
What is the responsibility of the Product Owner in crafting the Sprint Goal?
(choose the best answer)
A.
The Product Owner has no responsibility for the Sprint Goal. It is the sole responsibility of the Developers.
B.
The Product Owner cannot attend Sprint Planning without having documented the Sprint Goal in advance.
C.
The Product Owner should come to Sprint Planning with a business objective in mind and work with the Developers to craft the Sprint Goal.
D.
The Product Owner must work with stakeholders to set each Sprint's Goal.
E.
The Product Owner defines the scope for a Sprint and therefore also the Sprint Goal.
Your answer: