Question 76 - PSPO-I discussion
Your management has asked you to take the lead in the development of a new product. Six teams new to Scrum will build this product.
You have gathered a number of requirements and ideas into an early form of a Product Backlog. How would you minimize dependencies between the Scrum Teams?
(choose the best answer)
A.
You create an independent Product Backlog per Scrum Team.
B.
You divide Product Backlog items among the six Product Owners.
C.
You identify the dependencies and re-order the Product Backlog for the other five Product Owners.
D.
You work with the Developers on how to best analyze and break apart the work.
E.
You raise this as an impediment with the Scrum Master.