Why do the Developers need a Sprint Goal?

(choose the best answer)

A.
A Sprint Goal only gives purpose to Sprint O.
Answers
A.
A Sprint Goal only gives purpose to Sprint O.
B.
Sprint Goals are not valuable. Everything is known from the Product Backlog.
Answers
B.
Sprint Goals are not valuable. Everything is known from the Product Backlog.
C.
The Developers are more focused with a common yet specific goal.
Answers
C.
The Developers are more focused with a common yet specific goal.
D.
A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.
Answers
D.
A Sprint Goal ensures that all of the Product Backlog items selected for the Sprint are implemented.
Suggested answer: C

Explanation:

The Developers need a Sprint Goal because it gives them a common yet specific goal to focus on during the Sprint. This is because:

The Sprint Goal is a short-term objective that provides guidance and focus to the Scrum Team throughout the Sprint. It is a flexible and negotiable commitment that can be adjusted as more is learned throughout the Sprint.

The Developers are accountable for creating a "Done" Increment in every Sprint. They must ensure that every Product Backlog item they work on meets the Definition of Done before it is considered complete.

The Developers are self-managing professionals who organize and manage their own work. They decide how to best accomplish their work, rather than being directed by others outside the Scrum Team.

The Developers need a Sprint Goal to align their efforts and collaborate effectively as a team. The Sprint Goal helps them prioritize and optimize their work based on value and impact. The Sprint Goal also helps them cope with uncertainty and complexity by providing a clear direction and a shared purpose.

Other options, such as a Sprint Goal only giving purpose to Sprint 0, Sprint Goals being not valuable, or a Sprint Goal ensuring that all of the Product Backlog items selected for the Sprint are implemented, are not valid reasons why the Developers need a Sprint Goal. They may reflect a misunderstanding of what a Sprint Goal is or how Scrum works.

[Scrum Guide], page 15, section "Sprint Goal"

[Scrum Guide], page 7, section "Developers"

[Scrum Guide], page 10, section "Definition of Done"