Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item?
(choose the best two answers)
A.
Coach the Scrum Team to improve its skills, tools and environment over time and adjust the Definition of Done accordingly.
B.
Refocus the current Sprint on establishing the Scrum Team's environment instead of delivering an Increment.
C.
Encourage the Product Owner to accept partially done Increments until the situation improves.
D.
Have the Scrum Team establish a Definition of Done that is actually possible to achieve given current circumstances.
E.
Declare the Scrum Team not ready for Scrum.